Dillingen Power Plant

HR-Automation GmbH has worked on water-treatment automation at the Dillingen blast-furnace-gas power plant in a high-availability SIMATIC PCS 7 environment. A project in 2016 included an update to PCS 7 V8.1.

Project context

The project represents typical brownfield requirements in process industry: high availability, clearly defined interfaces and a controlled transition to a new system version.

  • Plant environment: Dillingen blast-furnace-gas power plant.
  • Subprocess: water treatment.
  • System environment: high-availability SIMATIC PCS 7.
  • Project status 2016: update to PCS 7 V8.1.